Our Role
PSCS, Main Contractor for the project
Services
Full Electrical Fit Out, management of trades, partners and collaborators on the project
Project Overview
This project for Our Lady of Lourdes Hospital Drogheda was carried out in a live operating environment with a requirement to minimise any degradation or service downtime. Given the live general hospital environment and the A&E facility, access to rooms and areas for upgrade work had to carefully managed and sequenced through working with bed management and hospital facility departments. This also meant ensuring the highest levels of health and safety, ensuring the public community and staff could access areas and rooms safely, ensuring no work areas with members of the public, ensuring no work material was left unattended with strict clean as you go procedures, ensuring dust minimisation via alupods and dust exactors and carefully scheduled and managed works including the A&E facility where there is a constant presence of public and staff.
Callaghan Electrical was responsible for all electrical contract works across the site, management of trades and partners.Key work included:
Disconnection of existing lighting and emergency lighting
Safe disposal of old lighting
Installation of new lighting and emergency lighting
Modification of existing wiring to include new fittings
Modifications to all existing distribution boards in the hospital
Installation of new lighting controls
Testing, commissioning and production of 'as installed' drawings
Installation of new Wi-Fi system in a section of the building
Delivered within a tight timeframe
Zero interruption to services or patient care
Management of trades and partners including decorators, cleaners and painters